Impact Fees and Permit Costs on a Custom Parkland Home
A custom house in Parkland triggers fees from the city, Broward County, the state and your utility. Here is who charges what, in what order, and where to get the current numbers before you sign a lot or builder contract.
Short answer
Building a custom house in Parkland involves a city park fee (listed as $3,850 on the city's new-residence checklist), Broward County school and road impact fees paid to the county before the city issues the permit, city building permit fees set by resolution, a 1% state surcharge on code-enforcement permit fees, and utility connection or septic charges. Florida law bars collecting impact fees before the building permit is issued. Get each current figure from the city, the county and your utility in writing before you commit.
A custom house in Parkland draws government charges from four directions: the City of Parkland, Broward County, the State of Florida and whichever utility serves the lot. The city's posted checklist for a new residence lists a $3,850 park fee added to the permit fee and asks for a Broward County receipt showing that school and road impact fees were paid. On top of those come the city's own building permit fees, a state surcharge, and water, sewer or septic costs. None of these numbers is fixed for long, so the useful skill is knowing who to ask and when each one comes due.
The fee map for one new house
| Charge | Who sets and collects it | When it shows up | Where to verify |
|---|---|---|---|
| School and road impact fees | Broward County | Paid to the county; receipt required for the city permit | Broward's development and environmental review (954-357-6666, ext. 2) |
| Park fee | City of Parkland | Included with the building permit fee | City checklist and Building Department |
| Building permit and plan review fees | City of Parkland, by resolution | At application and permit issuance | City fee schedule |
| State surcharge | Florida DBPR, collected through the permit | With permit fees | Section 553.721 |
| County review fees | Broward County | After county review is complete | Broward ePermits |
| Water and sewer connection, meter | Your utility | Meter receipt needed to pick up the permit | Utility serving the lot |
| Septic and well permits | Broward County Health Department | Before permit, in Pine Tree Estates and The Ranches | Health department |
The park fee and the impact-fee receipt both come from the city's new residential permit checklist. The same checklist notes that homes in Pine Tree Estates and The Ranches served by septic and wells need permits from the Broward County Health Department and are excluded from the water meter receipt requirement. The checklist is undated online, so confirm the park fee amount when you apply.
Order of operations: county first, then city
The sequence affects your schedule and your cash flow, because some fees are due well before construction starts.
- Broward County development and environmental review. According to Broward's ePermits page, the transportation concurrency step is where the county decides whether impact fees are due on new construction. You submit signed and sealed plans and a sealed survey online. Environmental review follows, checking for required licenses and open environmental enforcement.
- Approval certificates to the city. Each county review produces a certificate that must reach the city's Building Department within 30 days, or it expires and more fees apply.
- City permit application. Parkland now takes submittals through the MGO portal, after retiring its older system. The checklist requires separate applications for each discipline, two sets of sealed plans, energy calculations, product approvals, a tree removal permit if trees sit in the slab area, and Broward's environmental approval.
- Utility or septic step. A water meter receipt is needed to pick up the permit where public water serves the lot.
- Notice of Commencement. For work valued over $2,500, it must be recorded and posted before the first inspection.
Parkland and Broward run a joint ePermits OneStop process, so the county and city pieces can be submitted without a trip to the county's Plantation office.
What Florida's Impact Fee Act means for a buyer
Impact fees are governed statewide by section 163.31801. Several of its rules affect someone budgeting a Parkland build:
- Timing. A local government cannot require payment before the building permit is issued for the property.
- Notice and phase-ins. New or higher fees need at least 90 days' notice. Ordinary increases are capped at 50% and phased in: up to 25% over two years, more than 25% over four. Larger jumps require a recent study, workshops and a unanimous vote.
- Grandfathering. A new or increased fee generally does not apply to permit applications submitted before its effective date, unless the change lowers total fees.
- Replacement homes. Replacing an existing structure with the same use owes no impact fee unless the new building significantly increases size, intensity or capacity, and then only for the added demand.
- Credits. If you or a developer contributed land or improvements for the same type of facility, that contribution is credited dollar for dollar.
- Annual reports. Governments must publish yearly impact fee reports that include fee amounts by dwelling type, which is a useful cross-check on what you are quoted.
- Not covered. Water and sewer connection fees fall outside the Act.
The replacement rule matters in Parkland because some buyers purchase an older house on a large lot to demolish it. A new house much larger than the original may still owe a proportional fee, so ask before you count on zero.
Permit fees and the moving fee schedule
Parkland sets building fees by resolution rather than by ordinance, which means they change more often than buyers expect. The Building Department says permit fees were adjusted effective October 1, 2025, under Resolution 2025-054, and the city's fee schedule page links to Resolution 2026-046, adopted August 19, 2026, which added building department fees to the schedule amended in June 2026. Ask the Building Department for the current schedule, and ask how the permit fee for your plans will be calculated.
Florida adds a surcharge of 1% of permit fees related to enforcing the Florida Building Code, with a $2 minimum per permit, under section 553.721. Sub-permits for roofing, gas, fire sprinklers and low voltage can be pulled later, and each carries its own fee.
Utilities depend on the lot
Parkland does not run a single water utility. Depending on location, service may come from the City of Coconut Creek, the North Springs Improvement District or Parkland Utilities, Inc., and the large-lot areas often rely on wells and septic. Connection and meter charges therefore vary by parcel, and a septic system brings design, permit and installation costs instead. Our guide to water, sewer and septic in Parkland explains how to find the provider for a given address, and the large-lot search guide covers the Ranches and similar areas.
A pre-contract worksheet
Before you sign a lot purchase or a custom builder agreement, fill in these lines with written figures, not estimates from memory:
- County school impact fee and road impact fee for your planned house, from Broward County.
- City park fee, permit and plan review fees for your plan's size and value, from the Building Department.
- State surcharge, county review fees and sub-permit fees.
- Utility connection and meter fees, or septic and well permits and installation.
- Tree removal permits if the slab area has trees.
- Which of these the builder's price includes, in the contract.
Fee totals change over time, so date every figure and recheck it before you apply. This is general information; confirm details with the city, the county, your utility and, for contract language, a Florida real estate attorney.
Fold the fees into the full budget
Government fees are paid in cash or financed as construction soft costs, and either way they reduce what is left for the house itself. Start from the monthly payment you want after the build: Homvidia's affordability calculator turns that payment into a Parkland price for a house, which gives you a ceiling for lot, construction and fees combined. The anonymous mortgage breakdown shows how lenders may view your income for the eventual loan. If you would rather compare finished homes, our guide to new construction in Parkland covers builder deposits and first-year costs.
Questions buyers ask
Does a teardown in Parkland owe the same impact fees as a vacant lot?
Not necessarily. Section 163.31801 says no impact fee applies to replacing an existing structure with the same use unless the replacement significantly increases size, intensity or capacity, and then only in proportion to the increase. Ask the county and the city how they will apply that to your specific demolition and rebuild.
Who pays the impact fees on a custom build, me or the builder?
Whoever the contract says. Some custom builders include permits and fees in their price, others pass them through at cost, and some exclude them entirely. Ask for a line-item list of every government fee the builder expects and who pays each one.
Can Parkland or Broward raise impact fees after I buy my lot?
Yes, but Florida law requires at least 90 days' notice of a new or increased fee, caps most increases and requires phase-ins. Generally a new or higher fee does not apply to permit applications submitted before it takes effect, so timing your application can matter.
Are impact fees included in a construction loan?
Often they are budgeted as soft costs within the loan, but each lender sets its own rules. Give your lender the written fee estimates from the city and county so the budget and draw schedule account for them.
Sources
- City of Parkland — New residential, duplex and townhouse permit checklist
- City of Parkland — Building Department
- City of Parkland — Fee Schedule
- City of Parkland — Resolution 2026-046 amending the fee schedule
- Broward County — ePermits: Transportation concurrency and environmental review
- Florida Statutes — Section 163.31801, Impact fees
- Florida Statutes — Section 553.721, Surcharge